Prepare for the PRINCE2 Agile Foundation Exam with multiple choice questions and detailed explanations. Get familiar with the exam format and increase your knowledge to maximize success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What aspect of "zero time tolerance" reflects the deliverables expected from the project?

  1. Strict time limitations for all project phases

  2. An unwavering deadline for project completion

  3. Immediate delivery of prototypes without amendments

  4. Rigid adherence to the product schedule

The correct answer is: Immediate delivery of prototypes without amendments

The concept of "zero time tolerance" emphasizes the necessity for prompt and precise delivery of project outputs, particularly in agile environments. Immediate delivery of prototypes without amendments aligns with this principle as it demonstrates a commitment to ensuring that deliverables are produced on time. In embracing "zero time tolerance," the focus is placed on reducing delays and maintaining momentum within the project workflow. In this scenario, the option regarding immediate delivery emphasizes that the project team must produce results swiftly, without the luxury of revising prototypes after their initial iteration. This approach is crucial in dynamic project settings where responsiveness to customer feedback can lead to agile adaptations, but it demands stringent timelines that leave no room for slippage. Maintaining such a standard pushes teams to remain focused and efficient in their processes, which directly correlates with the core intent of zero time tolerance. The other options pertain to time management and deadlines but do not encapsulate the essence of "zero time tolerance" as effectively as the emphasis on immediate delivery of prototypes.